Question: A project has expected cash flows as shown below: Year Net Cash Flow 0 -25,000 1-4 5,000 5-7 4,000 8 8,000 9 7,000 If the
- A project has expected cash flows as shown below:
| Year | Net Cash Flow |
| 0 | -25,000 |
| 1-4 | 5,000 |
| 5-7 | 4,000 |
| 8 | 8,000 |
| 9 | 7,000 |
If the firm's discount rate is 12 percent, what is the NPV of this project?