Question: A project has fallen behind schedule due to a major catastrophic disaster that will require multiple rework activities to get the project back on track.

A project has fallen behind schedule due to a major catastrophic disaster that will require multiple rework activities to get the project back on track. What INITIAL action should the agency CM take to redirect the project goals?
Revise the current schedule.
Alert other parties to deviations from the re-established plan.
Recommend mitigation actions.
Develop a new schedule.