Question: A project has four activities: A , B , C , D . Their durations are 4 , 3 , 6 , and 7 days,
A project has four activities: A B C D Their durations are and days, respectively. What is the total completion time for the project?
A project has four activities: A B C D Their durations are and days, respectively. What is the total completion time for the project?
days, because this is the maximum activity time
It is not possible to determine the total completion time from the given information because the connections among the activities are unknown.
days, because this is the sum of the activity times
days, because this is the minimum activity time
Step by Step Solution
There are 3 Steps involved in it