Question: A project has four major activities. Activity A precedes activity B, activity C precedes activity D. 3-point estimates for activities are A(5.5, 11, 16.5 ),

A project has four major activities. Activity A precedes activity B, activity C precedes activity D. 3-point estimates for activities are A(5.5, 11, 16.5 ), B( 3.5, 7, 10.5 ), C( 3, 3, 3 ), D( 4, 4, 4 ) weeks. What probability would you assign to a project duration of more than 18 weeks?

Select one:

a. 1

b. 0.5

c. 0.8543

d. 0.3932