Question: A project has four major activities. Activity A precedes activity B, activity C precedes activity D. 3-point estimates for activities are A(8, 16, 24 ),
A project has four major activities. Activity A precedes activity B, activity C precedes activity D. 3-point estimates for activities are A(8, 16, 24 ), B( 5.5, 11, 16.5 ), C( 2, 4, 6 ), D( 11.5, 23, 34.5 ) weeks. What probability would you assign to a project duration of more than 27 weeks?
a.
0.5
b.
0.75
c.
0.858
d.
0.358