Question: A project has four major activities. Activity A precedes activity B, activity C precedes activity D. 3-point estimates for activities are A(5, 10, 15), B(

A project has four major activities. Activity A

A project has four major activities. Activity A precedes activity B, activity C precedes activity D. 3-point estimates for activities are A(5, 10, 15), B( 3.5, 7, 10.5), C(2,2,2), D( 2, 2, 2) weeks. What probability would you assign to a project duration of more than 17 weeks? O a 0.8931 Ob 1 Oc. 0.5 Od 0.4441