Question: A project has more than one critical path. This means that: Group of answer choices Shortening any one event cannot shorten the project duration Crashing

A project has more than one critical path. This means that: Group of answer choices Shortening any one event cannot shorten the project duration Crashing an event might shorten the project time The critical path was not calculated correctly Delaying an event on a critical path may not delay the project