Question: A project has seven activities: A , B , C , D , E , F , and G . Activities A , B ,

A project has seven activities: A, B, C, D, E, F, and G. Activities A, B, and D can start anytime. Activity A takes 3 weeks, activity B takes 5 weeks, and activity D takes 11 weeks. Activities A and B must be completed before activity C can start. Activity C requires 6 weeks to complete. Activities B, C, and D must be completed before activity E can start. Activity E requires 2 weeks. Activity F takes 4 weeks and can start as soon as activity C is completed. Activity E must be completed before activity G starts. Activity G requires 3 weeks. Activities F and G must be completed for the project to be completed. Which activities have float available?
Group of answer choices
Activity F has one week float.
Activity A has two weeks float; activity F has one week.
Activity A has eight weeks float.
There is no float available in the project.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!