Question: A project has several work packages equaling $ 2 , 0 0 0 , 0 0 0 . 0 0 and a contingency reserve of

A project has several work packages equaling $2,000,000.00 and a contingency reserve of 20% and a management reserve of 10%. Calculate the project budget.