Question: A project has six tasks which are required for completion: Tasks A , B , C , D , E and F . The relationship

A project has six tasks which are required for completion: Tasks A, B, C, D, E and F. The relationship between the tasks is described below:
Task A takes 8 weeks. Task B takes 3 weeks. Task A must be completed before beginning Task C. Task C takes 7 weeks. Both Tasks A and B must be completed before beginning Task D. Task D takes 3 weeks. Task E takes 4 weeks. In order to begin Task E, Task C must first be completed. Task F takes 6 weeks. In order to begin Task F, Task D must first be completed.
Which tasks are on critical path?