Question: A project has six tasks which are required for completion: Tasks A , B , C , D , E and F . The relationship
A project has six tasks which are required for completion: Tasks A B C D E and F The relationship between the tasks is described below:
Task A takes weeks. Task B takes weeks. Task A must be completed before beginning Task C Task C takes weeks. Both Tasks A and B must be completed before beginning Task D Task D takes weeks. Task E takes weeks. In order to begin Task E Task C must first be completed. Task F takes weeks. In order to begin Task F Task D must first be completed.
Which tasks are on critical path?