Question: A project has the activities listed in the chart below: Activity Description Predecessor(s) Time (weeks) A Collect Components - 2 B Modify Frame - 3
A project has the activities listed in the chart below:
| Activity | Description | Predecessor(s) | Time (weeks) |
| A | Collect Components | - | 2 |
| B | Modify Frame | - | 3 |
| C | Assemble Components | A | 2 |
| D | Assemble Unit | A, B | 4 |
| E | Bake Assembly | C | 4 |
| F | Install add-ons | C | 3 |
| G | Run Assembly | D, E | 5 |
| H | Inspect and test | F, G | 2 |
What is the critical path of the project?
B, D, F, H
A, D, F, H
B, D, G, H
A, C, E, G, H
B, D, F, H
Using the information in the project activity matrix shown in question #8, what is the total project time in weeks?
Group of answer choices
13
12
15
14
16