Question: A project has the activity diagram shown below. What is the shortest time the project can be completed? table [ [ Activity , Duration

A project has the activity diagram shown below. What is the shortest time the project can be completed?
\table[[Activity,Duration (Months),Dependency],[A,5,n/a],[B,2,n/a],[C,3,A],[D,2,B],[E,4,B],[F,5,C,D],[G,3,E],[H,1,F],[I,3,F,G]]
15 months
13 months
16 months
14 months
A project has the activity diagram shown below.