Question: A project has the activity duration and cost information indicated in the table where all times are in weeks. there is a penalty of $4,000
A project has the activity duration and cost information indicated in the table where all times are in weeks. there is a penalty of $4,000 per week for every week the project exceeds 37 weeks. what is the lowest total cost for completing this project?