Question: A project has the following activities, with specified precede and expected durations (in hours). Activity Precedent Duration A - 6.0 B - 7.2 C A
A project has the following activities, with specified precede and expected durations (in hours).
| Activity | Precedent | Duration |
| A | - | 6.0 |
| B | - | 7.2 |
| C | A | 5.0 |
| D | B,C | 6.0 |
| E | B,C | 4.5 |
| F | D | 7.7 |
| G | E,F | 4.0 |
(note:answer 9.2 wrong)