Question: A project has the following cash flows. The required return for the project is 10% Cash Flow -$100,000 $30,000 $15,000 $20,000 $40,000 $40,000 Time 0
A project has the following cash flows. The required return for the project is 10%
| Cash Flow | -$100,000 | $30,000 | $15,000 | $20,000 | $40,000 | $40,000 |
| Time | 0 | 1 | 2 | 3 | 4 | 5 |
a. Calculate the project's payback period.
b. Calculate the project's NPV.
c. Calculate the project's IRR.
d. Calculate the project's Profitability Index.