A project has the following information:
a. Construct a tracking Gantt chart, using MS Project if possible.
b. Highlight project status on day 12 using the tracking option and assuming that all tasks to
date have been completed on time. Print the output file.
c. Highlight the project's status on day 12 but assume that activity D has NOT yet begun. What
would the new tracking Gantt chart show? Print the output file.
 A project has the following information: a. Construct a tracking Gantt