Question: A project has the following information ( FS dependencies ) . What is the duration of the critical path? ( 5 marks ) ( Hint:

A project has the following information (FS dependencies).
What is the duration of the critical path? (5 marks)(Hint: you do not need to do a forward and backward pass)
What is the probability of completing the project between 13 and 21 time periods? (15 Marks). Show your calculations.
Optimistic Most Likely Pessimistic
Activity Time Time Time Predecessors
A 135
B 234 A
C 123 A
D 135 B
E 147 B
F 123 C
G 147 E,F
H 234 D
I 123 G,H

Step by Step Solution