Question: A project has the following time schedule. table [ [ Activity , Time ( months ) ] , [ 1 - 2 , 2

A project has the following time schedule.
\table[[Activity,Time (months)],[1-2,2],[1-3,2],[1-4,1],[2-5,4],[3-6,8],[3-7,5],[4-6,3],[5-8,1],[6-9,5],[7-8,4],[8-9,3]]
(i) Construct a CPM network.
(ii) Determine the critical path.
(iii) Compute the project completion time.
(iv) Compute total float for each activity.