Question: A project has two activities A and B. The expected cost for A and B are $100,000 and $50,000, respectively. At a certain point, the
A project has two activities A and B. The expected cost for A and B are $100,000 and $50,000, respectively. At a certain point, the expected complete percentages for A and B should be 100% and 70%, respectively. However, the actual complete percentages for A and B are 90% and 100%, respectively. Based on the above information, compute the BCWS
A project has two activities A and B. The expected cost for A and B are $100,000 and $50,000, respectively. At a certain point, the expected complete percentages for A and B should be 100% and 70%, respectively. However, the actual complete percentages for A and B are 90% and 100%, respectively. Based on the above information, compute the BCWP.
Based on the same information above and assume the actual cost is $160,000, compute the Cost Performance Index (CPI).
Based on the same information above, compute the Schedule Performance Index (SPI)
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
