Question: A project involves four activities A 1 , A 2 , A 3 and A 4 . Characteristics of these activities are as follows: A

A project involves four activities A1, A2, A3 and A4. Characteristics of these activities are as follows:
A1: This activity requires 50 units of work to be completed. A worker can complete 2 units of work in a day.
A2: This activity requires 75 units of work to be completed. A worker can complete 3 units of work in a day.
A3: This activity requires 60 units of work to be completed. A worker can complete 4 units of work in a day.
A4: This activity requires 11 units of work to be completed. A worker can complete 1 unit of work in a day.
A1, A2 and A3 can be scheduled in parallel or in any sequence. However, activity A4 can be started only after the activities A1, A2 and A3 are completed. No activity can be completed within a fraction of a day, that is, workers doing an activity will be released only at the end of the day and not in between. All the activities have to be completed within 7 days. A worker is paid Rs.500 per day for all the days for the entire duration of the project, including any days the worker is idle. Work out the schedule such that the labour cost is the minimum.
The number of workers required:

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Civil Engineering Questions!