Question: A project involves the design and building of four software modules, called A , B , C , and D respectively. The estimated effort for

A project involves the design and building of four software modules, called A, B, C, and D respectively. The estimated effort for each of the modules is 20 days for A,18 for B,15 for C and 12 for D respectively.
The firm that is undertaking the work assumes for the purpose of earned value analysis (EVA) that design takes up 30% of the effort, coding 40% and testing 30%.
On the day that this EVA is conducted, the modules A, B, and C should have been
completed in full. In fact, the situation is as follows:
i) Explain what is meant by planned value (PV), earned value (EV), and actual cost (AC) in EVA.
ii) Calculate the PV, EV, and AC for the above project based on its current status (i.e., on the day of the EVA) given in Table 3.
iii) For the project in Table 3, calculate the
a) Schedule and cost variances
b) Cost performance and schedule performance indicator
iv) What general conclusions might be drawn from the above figures about the overall state of the project?
v) If a project is behind schedule and/or over budget, what could be done to get it back on target? Discuss the impact (undesired effects) of the suggested actions.
A project involves the design and building of

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!