Question: A project involves the design and building of four software modules, called A , B , C , and D respectively. The estimated effort for
A project involves the design and building of four software modules, called A B C and D respectively. The estimated effort for each of the modules is days for A for B for C and for D respectively.
The firm that is undertaking the work assumes for the purpose of earned value analysis EVA that design takes up of the effort, coding and testing
On the day that this EVA is conducted, the modules A B and C should have been
completed in full. In fact, the situation is as follows:
i Explain what is meant by planned value PV earned value EV and actual cost AC in EVA.
ii Calculate the PV EV and AC for the above project based on its current status ie on the day of the EVA given in Table
iii For the project in Table calculate the
a Schedule and cost variances
b Cost performance and schedule performance indicator
iv What general conclusions might be drawn from the above figures about the overall state of the project?
v If a project is behind schedule andor over budget, what could be done to get it back on target? Discuss the impact undesired effects of the suggested actions.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock