Question: A project is 50% completed. An essential project team member requests two (2) months leave for personal matters. What should the project manager do first?
A project is 50% completed. An essential project team member requests two (2) months leave for personal matters. What should the project manager do first? Group of answer choices Assess how the leave will impact the project. Check with this team member to see if the leave can be postponed. Refer to the resource management plan. Discuss the issue with the functional manager and request a replacement