Question: A project is at the multi-functional planning phase. The project manager realizes that producing a complex application is not feasible with the current number of

A project is at the multi-functional planning phase. The project manager realizes that producing a complex application is not feasible with the current number of resources and decides to hire more resources for the production of the application. The project manager identifies temporary resources and signs a service level agreement (SLA) with them. Which risk response strategy does this scenario exemplify? Select one. Avoid Mitigate Accept O Transfer