Question: A project is comprised of five tasks. The precedence relationships and crash information are given in the following table. Activity Crash cost (thousand $SS) 90

A project is comprised of five tasks. The

A project is comprised of five tasks. The precedence relationships and crash information are given in the following table. Activity Crash cost (thousand $SS) 90 Immediate predecessors N/A N/A A B, C A B D E Normal time (days) 3 6 4 6 8 Crash time (days) 1 3 2 2 3 Normal cost (thousand SSS) 50 60 40 40 70 90 100 100 120 If you need to shorten the project completion time by four days in total, how much is the total minimum crash cost (in $$$)