Question: A project is delayed and the risk manager is working on a new plan for the remaining work. Based on previous results, the project team
A project is delayed and the risk manager is working on a new plan for the remaining work. Based on previous results, the project team is having frequent issues with quality due to lack of experience in the technology used, requiring additional testing effort and rework. How should the risk manager and team respond to this type of risk in the future? Avoid the risk by eliminating rework waste. Transfer the risk with contractual clauses. Accept the risk with contingency reserves. Mitigate the risk with management reserves