Question: A project is estimated to cost 16,200. It is expected to a life of 3 years and generate cash inflows of rs 8000 ,rs 7000
A project is estimated to cost 16,200. It is expected to a life of 3 years and generate cash inflows of rs 8000 ,rs 7000 and rs 6000 respectively. Calculate IRR.
Present value of rupee one at varying discount rate for period of 3 years.
Years 13% 14% 15% 16%
1 0.8850 0.8772 0.8696 0.8621
2 0.7831 0.7695 0.7561 0.7432
3 0.6930 0.6750 0.6575 0.6407