Question: A project is following a predictive methodology. A key stakeholder from the quality department wants to know more about how the process tailoring was done

A project is following a predictive methodology. A key stakeholder from the quality department wants to know more about how the process tailoring was done by the project team. Additionally, the stakeholder would like to know the rationale for selecting processes, their implementation-level details, and how they will be used to manage interdependencies. Which document should the Project Manager refer the stakeholder to?