Question: A project is officially authorized when _ _ _ _ _ _ _ _ _ _ . A the preliminary budget is approved B the
A project is officially authorized when
A
the preliminary budget is approved
B
the customer signs the contract
C
the project manager has been assigned
D
Collecting and documenting lessons learned is part of which Process Group?
A
Planning
B
Monitoring & Controlling
C
Executing
D
Closing