Question: A project is scheduled to last four weeks. This schedule is based on a crew of 7 workers (Crew A) working 10 hours per
A project is scheduled to last four weeks. This schedule is based on a crew of 7 workers (Crew A) working 10 hours per day for 5 days per week. The wage is $16 per hour for regular hours. Beyond 8 hours per day or 40 hours per week, the pay is increased by a multiplier of 1.25, i.e., $20 per hour. (a) Determine the number of labor hours actually worked based on this schedule. (Man hours = _____) (b) From the table, use the productivity rates for weeks 1 and 2, then 3 and 4 to calculate the effective labor hours at standard productivity. (Effective labor hours = (c) Calculate the size of the crew (Crew B) required to do a standard 40 hour week over the same 4- week period. (Use whole numbers for the crew size - the weeks can be fractional) (Size of Crew B=_ (d) Calculate the labor cost of Crew A: (Cost of Crew A =$________) (e) Calculate the labor cost of Crew B: (Cost of Crew B =$___________
Step by Step Solution
3.46 Rating (153 Votes )
There are 3 Steps involved in it
a Number of Labor Hours Actually Worked Crew A consists of 7 workers working 10 hours per day 5 days ... View full answer
Get step-by-step solutions from verified subject matter experts