Question: A project is shown below, and the project manager is asked to develop an optimal time-cost solution: Activity ID Predecessor Estimated Duration (days) Crash Time
A project is shown below, and the project manager is asked to develop an optimal time-cost solution:
| Activity ID | Predecessor | Estimated Duration (days) | Crash Time (days) | Cost/Week for crash |
| A |
| 6 | 6 | 0 |
| B | A | 10 | 8 | $500 |
| C | A | 5 | 4 | $300 |
| D | C | 4 | 1 | $700 |
| E | B, D | 9 | 7 | $600 |
| F | E | 2 | 1 | $800 |
- Determine the critical path, total time, and slack ager? Describe in bullet points.