Question: A project is shown below, and the project manager is asked to develop an optimal time-cost solution: Activity ID Predecessor Estimated Duration (days) Crash Time

A project is shown below, and the project manager is asked to develop an optimal time-cost solution:

Activity ID

Predecessor

Estimated Duration (days)

Crash Time

(days)

Cost/Week for crash

A

6

6

0

B

A

10

8

$500

C

A

5

4

$300

D

C

4

1

$700

E

B, D

9

7

$600

F

E

2

1

$800

  1. Determine the critical path, total time, and slack ager? Describe in bullet points.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!