Question: A project is under budget when:Required to answer. Single choice. (1 Point) CPI > 1 or CV > 0 SPI > 1 or SV <
A project is under budget when:Required to answer. Single choice.
(1 Point)
CPI > 1 or CV > 0
SPI > 1 or SV < 0
CPI < 1 or CV < 0
SPI < 1or CV > 0
CPI < 1 or CV > 0