Question: A project lead is managing an agile project. The project activities, which have been placed in a backlog, still need to be refined and prioritized.

A project lead is managing an agile project. The project activities, which have been placed in a backlog, still need to be refined and prioritized. What should the project lead use for backlog refinement considering the sprints are 2 weeks long? Sixty minutes every sprint going through stories that are higher priority. Ninety minutes every three sprints going through stories that are higher priority. Ninety minutes every three sprints going through stories with higher story points. Sixty minutes every sprint going through stories with higher story points