Question: A project manager and key team members were preparing a RACI chart for the major project work packages and activities. In each row they only
A project manager and key team members were preparing a RACI chart for the major project work packages and activities. In each row they only assigned one "A" (for Accountable) to a single resource. Why did they feel it was necessary for only one person to be assigned the primary accountability for each activity?
| |||
| |||
| |||
|