Question: A project manager determines that a critical path activity is going to be delayed. The team proposes a fallback plan that could get the project
A project manager determines that a critical path activity is going to be delayed. The team proposes a fallback plan that could get the project back on track; however, the plan would require an additional cost to an already tight budget.
What should the project manager do
O Communicate the delay to stakeholders and maintain the existing budget baseline.
Add additional resources to the project to fast track certain activities and reduce delays. O Evaluate the fallback plan proposed by the team and submit a change request, if required. Use the existing budget for executing the fallback plan and update the baseline.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
