Question: A project manager develops a project management plan and schedule based on an agreed - upon project lifecycle of 1 6 months. Later, due to
A project manager develops a project management plan and schedule based on an agreedupon project lifecycle of months. Later, due to changing business requirements, the project sponsor requests completion within nine months. How should the project manager respond to this proposed change?
Group of answer choices
Work with key stakeholders and project team members to discuss the business requirements.
Modify the original project schedule to meet the revised deadline.
Perform an impact evaluation of this change request and evaluate the change in scope.
Meet individually with project team members to discuss which aspects of the project can be removed from the scope.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock