Question: A project manager discovers that a contractor is performing additional, but necessary, work that was approved by a team member without the project managers knowledge.

A project manager discovers that a contractor is performing additional, but necessary, work that was approved by a team member without the project managers knowledge. What should the project manager do to avoid this situation in the future?

  • A. Meet the team member to review how the change control process works
  • B. Ask the team to ensure that work is done only on approved, in scope items
  • C. Meet with the team member and the contractor to discuss the change
  • D. Review the requirements list and resource allocation to determine why the work was not in the scope

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!