Question: A project manager for a construction firm meets with stakeholders. All stakeholders agree on a 2 0 - month lifecycle for a project. After work

A project manager for a construction firm meets with stakeholders. All stakeholders agree on a 20-month lifecycle for a project. After work has begun, the project manager learns that stakeholders would like project completion within no more than 16 months. Which step should the project manager not take?
Group of answer choices
Add team members to work more quickly.
Negotiate with stakeholders to reduce project requirements.
Advise against modifying the timeline.
Reduce the scope and crash the schedule.