Question: A project manager for a small construction company has a project that was budgeted for R 1 3 0 0 0 0 0 over a

A project manager for a small construction company has a project that was budgeted for R1300000 over a six week period. According to her schedule, the project should have cost R 600000 to date. However, it has cost R 900000 to date. The project is also behind schedule, because the original estimates were not accurate. Who has the Primary responsibility to solve this problem?
Question 16 options:
A)
Senior management
B)
Manager of the project management office
C)
Project sponsor
D)
Project manager