Question: A Project manager had a complex problem to solve and decided what needed to be done. A few months later, the problem resurfaced. What did

A Project manager had a complex problem to solve and decided what needed to be done. A few months later, the problem resurfaced. What did the project manager MOST likely NOT do?
Question 26 options:
Use an Ishikawa diagram.
Proper risk analysis
Confirm the decision solved the problem.
Have the project sponsor validate the decision.