Question: A project manager has an agreement with a third-party supplier to deliver parts in six months. During the invitation phase, the project is canceled. However,
A project manager has an agreement with a third-party supplier to deliver parts in six months. During the invitation phase, the project is canceled. However, the supplier has already you started to work on the order what should the project manager do next?
- A. Direct the supplier to stop work immediately
- B. Review the contracts termination clause
- C. The Conduct a supplier performance evaluation
- D. Update the procurement management plan