Question: a project manager has been given a critical time frame of 5 days and a maximum contingency reserve of $ 1 0 0 , 0

a project manager has been given a critical time frame of 5 days and a maximum contingency reserve of $100,00. The project manager then wrote up a plan of action based on the best information that was abailable. Overall, there were five things that had to be done, and each one cost $20,000 and took a day. After three days of work, the project manager had finished two tasks and spent $80,000. What comes next for the project manager?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!