Question: A project manager has determined the following information for a project to be completed: Activities Successors immediately Duration (in days) A B 2 B C
A project manager has determined the following information for a project to be completed:
| Activities | Successors immediately | Duration (in days) |
|---|---|---|
| A | B | 2 |
| B | C | 2 |
| C | AND | 5 |
| D | F | 2 |
| AND | 3 | |
| F | AND | 4 |
Complete the following table:
| Activities | Duration (in days) | DH | FH | DT | FT | MT | ML |
|---|---|---|---|---|---|---|---|
| A | |||||||
| B | |||||||
| C | |||||||
| D | |||||||
| AND | |||||||
| F |
where DH is the earliest start date; FH is the earliest finish date; DT is the latest start date; FT is the latest end date; MT is the total margin; and ML is the free margin of activities. ( 10 points )
Points are awarded for the approach.