Question: A project manager has prepared a network for a small project. The following activities can be crashed at the indicated costs: A time-independent, indirect cost

A project manager has prepared a network for a small project. The following activities can be crashed at the indicated costs:

A time-independent, indirect cost of $1400 and a cost of $200 per day is associated with this project and its execution.

A project manager has prepared a network for a

As a contractor, determine the following:

  1. Shortest project duration (days) in the most cost-efficient way:
  2. Total cost associated with your answer to part a:
A project manager has prepared a network for a small project. The following activities can be crashed at the indicated costs: Activity Predecessors Normal duration Normal cost Crash duration Crash cost (days) ($) (days) ($) A 2 1000 2 1000 B A 5 900 4 950 3 550 3 550 D A 3 1200 1 1300 E B, C 3 3 2. 3 400 1 700 F D 500 1 600 G E, F 2 400 1 700 A time-independent, indirect cost of $1400 and a cost of $200 per day is associated with this project and its execution. As a contractor, determine the following: a. Shortest project duration (days) in the most cost-efficient way: b. Total cost associated with your answer to part a

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!