Question: A project manager has two engineers assigned to the project and does not have access to more even if the result means extending the completion
A project manager has two engineers assigned to the project and does not have access to more even if the result means extending the completion date on the project. The project manager is managing a(n) ________.
Multiple Choice
-
time-constrained project
-
people-constrained project
-
engineer-constrained project
-
resource-constrained project
-
human-constrained project