Question: A project manager has updated the project schedule. With the latest changes, a green arrow appears in the gantt chart. What does this indicate? Select

A project manager has updated the project schedule. With the latest changes, a green arrow appears in the gantt chart. What does this indicate? Select the best answer.
Question 25 options:
the manager needs to review the task changes
a deadline date has been added to the project
a "must start on" constraint was added
the change created float on the updated activities
the lead time was changed