Question: A project manager has worked closely with the project team to develop subsidizer management plans identified as necessary. Using various estimating techniques and guidance of
A project manager has worked closely with the project team to develop subsidizer management plans identified as necessary. Using various estimating techniques and guidance of experts, they have also carefully documented the scope, generated a project schedule and budget. What is the project manager likely to do next?
A) Baseline the plan
B) Facilitate a kick off meeting
C) Begin execution of the work
D) Publish the plan