Question: A project manager have just learned that a supplier ha sa history of missing deadlines. The supplier is defensive when asked about this. The project
A project manager have just learned that a supplier ha sa history of missing deadlines. The supplier is defensive when asked about this. The project manager decides to find a new vendor. What kind of risk mitigation strategy is this? Transferring risk, Avoiding risk, Accepting risk, Controlling risk