Question: A project manager in a construction company has been assigned to a project to build four government buildings under a fixed price contract. Her company
A project manager in a construction company has been assigned to a project to build four government buildings under a fixed price contract. Her company has decided to outsource part of the project to an external contractor. She has finished creating the procurement statement of work, has come up with a selected seller and signed a contract to carry out the procurement. What is the next task she should do? (For Ref Only, Question #: PM-02926) Group of answer choices Managing procurement relationships and monitoring contract performance Obtaining seller response and awarding a contract Procurement negotiations Close project or phase