Question: A project manager is concerned about rework, specifically about having to iterate on two activities that are on the critical path. A consultant tells the
A project manager is concerned about rework, specifically about having to iterate on two activities that are on the critical path. A consultant tells the project manager to not worry, as the effect of uncertain activity times is likely to dominate the effect of iteration. The project manager disagrees. Who is right?
A The Project Manager
B The Consultant
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts