Question: A project manager is consolidating information for all the work streams within a data center and IT service transition project. To ensure the project delivers

  1. A project manager is consolidating information for all the work streams within a data center and IT service transition project. To ensure the project delivers value quickly, the project manager will assess a large number of consolidated project schedules. Which two actions should the project manager take with regard to schedule analysis? (choose two) PLEASE CHOOSE 2 Answer not only one
  1. Review with subject matter experts (SMEs) to ensure they have contributed to the schedule development.
  2. Evaluate the schedules for interdependencies to establish the critical path.
  3. Look for gaps in the different schedules to determine which major risks might evolve over time.
  4. Evaluate the master schedule and perform fast tracking and task crashing.
  5. Review the project schedules to ensure that all tasks end with milestones.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!